Tampa Airport Interchanges -- SR 60 (completed March 2010)

Project Description

Financial Project # 255844
Project Length: 3 miles
Estimated Construction Cost: $230 million
Contractor: Flatiron-Tidewater Skanska, a Joint Venture
Start Date: August 15, 2005
Completed: March 31, 2010

About this Project
The Florida Department of Transportation (FDOT) has completed improvements to State Road 60/Memorial Highway from I-275 to the Courtney Campbell Parkway interchange, in the vicinity of Tampa International Airport (TPA). The project also extended west one mile onto the Courtney Campbell Parkway (S.R. 60) and north to the Veterans Expressway (Toll 589). This entire project was known as the Tampa Airport Interchanges project. See map.

The Spruce Street/S.R. 60 interchange was improved to a four-level interchange and the Courtney Campbell/S.R. 60 interchange was improved to a three-level directional interchange. This configuration eliminated S.R. 60 traffic signals within the Courtney Campbell interchange and on the causeway at the Hyatt entrance (Bayport Drive). It also provided a two lane frontage road system for access to the Hyatt property. The new interchange configuration features the separation of local and express traffic with collector/distributor (C/D) roads and express lanes. This system is also expected to help reduce congestion on the interstate ramps within the area and improve access to Tampa International Airport.

Directions out of TPA to connecting roads:
To help get you out of Tampa International Airport and make the connection to major roads, we have step-by-step maps to guide you:
Click here to go to the directions page.

"Before & After" Aerial Photos
To get a view of the dramatic changes that were constructed to this roadway system, click here to view pre-construction aerial photos along with computer-enhanced versions of these photos that show artist renderings of the improvements.

Aerials (straight down views) Photos (various views)

Presentation Board View of the Project
For another view of the area, click here to view presentation boards of the entire project area.

"Drive-Through" Video
We also offer a computer-enhanced "driving" video of what the completed project looks like (made prior to construction). This video takes you through many of the driving movements that are now in place. Click here to view the video.

Lane Closure Hours were
State Road 60
* Single Lane: 8:30 p.m. to 5:30 a.m.
* Double Lane: 11 p.m. to 5 a.m.

Spruce Street
* Single Lane: 8:30 p.m. to 5:30 a.m.
* Double Lane: 11 p.m. to 5 a.m.

George Bean Parkway
* 11 p.m. to 6 a.m.

State Road 589 (Veterans Expressway) Northbound
* Single Lane: 8:30 p.m. to 5:30 a.m.
* Double Lane: 11 p.m. to 5 a.m.

State Road 589 (Veterans Expressway) Southbound
* Single Lane: 8:30 p.m. to 5 a.m.
* Double Lane: 11 p.m. to 5 a.m.

Night Detours
* 10:30 p.m. to 4:30 a.m.