Southbound I-75 Exit Ramp Extension & Widening at SR 60 (completed November 2014)
Project Description
Financial Project # 419194-1
Project Length: 1 mile
Estimated Construction Cost: $14.2 million
Contractor: Cone & Graham, Inc.
Start Date: April 12, 2013
Completed: November 24, 2014
About this Project
The Florida Department of Transportation's (FDOT) contractor lengthened and widened the southbound I-75 exit ramp to State Road 60 (SR 60).
Now completed, the final traffic pattern looks like this: The southbound I-75 mainline remains as before construction with three through-lanes. The southbound exit to SR 60 now has an auxiliary lane that begins about one mile north of the previous exit point and becomes a two-lane ramp. This double-lane ramp replaced the prior single-lane ramp and extends toward SR 60 connecting to the four-lane portion on the ramp at SR 60.
This project also included rebuilding the southbound I-75 mainline bridge decks over the CSX railroad and Woodberry Road.
Lane Closure Hours:
Mainline I-75: 9:00 p.m. to 6:30 a.m.
Contact Person(s)
Public & Media Contact
John McShaffrey, APR
Interstate Construction Office
(813) 975-6930
Related Projects (FDOT)
- Other FDOT I-75 Projects
- Other FDOT Hillsborough County Projects
- Other FDOT Pasco County Projects
- Other FDOT Hernando County Projects
- Other FDOT Hillsborough/Pasco County Projects
- Other FDOT Tampa Bay Area: FDOT District 7 Projects
- Other FDOT Hillsborough County/Pasco County Projects
- Other FDOT Pasco/Hernando/Sumter counties Projects
Southbound I-275 exit to westbound SR 60 may be closed at night
Posted 4/15/2016 8:00:00 AM
Left turn lanes reopened on Thonotosassa Road, south of I-4
Posted 4/15/2016
Night lane closures on I-75 in upper Pasco County
Posted 4/20/2016
What is TBI?
TBi stands for Tampa Bay Interstates - a program of the Florida Department of Transportation, District 7.