I-75 Ramp Improvements at the Gibsonton Drive Interchange (completed September 2012)
Project Description
Financial Project Number: 425946-1-52-01
Project Limits: Between interchange ramps
Project Length: .86 miles
Construction Cost: $1.5 million
Contractor: Ajax Paving
Start Date: January 3, 2012
Completion Date: September 30, 2012
About this Project
The Florida Department of Transportation's (FDOT) contractor widened the southbound I-75 exit ramp and the entrance ramp onto northbound I-75. The left turn lanes from Gibsonton Drive onto I-75 were also widened.
Other work in this project included some drainage improvements, a new overhead sign structure on the southbound exit ramp, new traffic signals on the west side of I-75 at Gibsonton Drive, and pavement milling and resurfacing.
Traffic Flow
There was daytime work, but the construction plans were designed so that all mainline travel lanes were open on I-75 and Gibsonton Drive during peak traffic hours.
Night Work
In order to maintain the construction schedule, and to minimize the impact to the traveling public, all lane closures and some construction work were done during nighttime hours.
Lane Closure Hours
10 p.m. to 5 a.m.
Related Projects (FDOT)
- Other FDOT I-75 Projects
- Other FDOT Hillsborough County Projects
- Other FDOT Pasco County Projects
- Other FDOT Hernando County Projects
- Other FDOT Hillsborough/Pasco County Projects
- Other FDOT Tampa Bay Area: FDOT District 7 Projects
- Other FDOT Hillsborough County/Pasco County Projects
- Other FDOT Pasco/Hernando/Sumter counties Projects
Southbound I-275 exit to westbound SR 60 may be closed at night
Posted 4/15/2016 8:00:00 AM
Left turn lanes reopened on Thonotosassa Road, south of I-4
Posted 4/15/2016
Night lane closures on I-75 in upper Pasco County
Posted 4/20/2016
What is TBI?
TBi stands for Tampa Bay Interstates - a program of the Florida Department of Transportation, District 7.