Click on an icon above to learn about projects on that road.
I-75 from Lockhart Road to Withlacoochee River (resurfacing, completed June 2012)
Project Description
Financial Project Number: 425085-1
Project Limits: from Lockhart Road to Withlacoochee River Bridge
Project Length: 7.6 miles
Estimated Construction Cost: $4.8 million
Contractor: D.A.B. Constructors, Inc.
Start Date: July 11, 2011
Completed: June 13, 2012
About this Project
The Florida Department of Transportation's (FDOT) contractor removed (milled) and resurfaced (paved) the asphalt travel lanes of I-75 from Lockhart Road to the Withlacoochee River Bridge in Hernando County.
The project also included resurfacing three of the four ramps at the State Road 50 (Cortez Blvd.) interchange. Closures on these ramps were limited and took place during the regular closure hours, Monday through Thursday nights. Only the southbound I-75 Exit 301 to State Road 50 was NOT resurfaced as it had been done prior to this project.
Traffic Flow
The construction phasing was designed so that all existing lanes of traffic and interchange ramps were open on I-75 during peak traffic hours.
Night Work
In order to maintain the construction schedule, and to minimize the impact to the traveling public, lane closures and construction work were done during nighttime hours.
Lane Closure Hours
7:30 p.m. to 7:30 a.m.
Fact Sheets
Related Projects (FDOT)
- Other FDOT I-75 Projects
- Other FDOT Hillsborough County Projects
- Other FDOT Pasco County Projects
- Other FDOT Hernando County Projects
- Other FDOT Hillsborough/Pasco County Projects
- Other FDOT Tampa Bay Area: FDOT District 7 Projects
- Other FDOT Hillsborough County/Pasco County Projects
- Other FDOT Pasco/Hernando/Sumter counties Projects
Southbound I-275 exit to westbound SR 60 may be closed at night
Posted 4/15/2016 8:00:00 AM
Left turn lanes reopened on Thonotosassa Road, south of I-4
Posted 4/15/2016
Night lane closures on I-75 in upper Pasco County
Posted 4/20/2016