I-275 Shoulder Barrier Wall near the Howard Frankland Bridge (completed November 2010)
Project Description
Financial Project Numbers: 427033-1 & 427033-2
Project Limits: Various locations along the seawall at each end of the Howard Frankland Bridge
Project Length: 1/2 mile
Estimated Construction Cost: $585,000
Contractor: Pepper Contracting Services, Inc.
Start Date: June 16, 2010
Completed: November 13, 2010
About this Project
The Florida Department of Transportation has completed improving the barrier system at each end of the Howard Frankland bridge by replacing the existing fence with concrete barrier wall. The barrier will help with erosion control and help prevent vehicles that leave the roadway from entering the water.
Improvement Highlights
- Gravel fill was placed beneath the new barrier and behind the existing seawall in order to prevent future storm damage.
Traffic Flow
Traffic was not impacted as no closures were needed for this work.
Southbound I-275 exit to westbound SR 60 may be closed at night
Posted 4/15/2016 8:00:00 AM
Left turn lanes reopened on Thonotosassa Road, south of I-4
Posted 4/15/2016
Night lane closures on I-75 in upper Pasco County
Posted 4/20/2016