I-75 from Pasco County line to Lockhart Road (resurfacing, completed Sept. 2010)
Project Description
Financial Project Number: 422443
Project Limits: from Pasco/Hernando counties line to south of Lockhart Road
Project Length: 3.8 miles
Construction Cost: $5 million
Contractor: D.A.B. Constructors, Inc.
Start Date: March 7, 2010
Completed: September 16, 2010
About this Project
The Florida Department of Transportation's contractor has completed milling and resurfacing I-75 from the Pasco-Hernando counties line to south of Lockhart Road in Hernando County.
Improvement Highlights
- Fixed the deteriorating condition of the existing roadway for a smoother and better riding surface.
- Constructed a bridge pier protection system at the Church Road overpass.
- Replaced guardrail where needed.
The construction phasing was designed so that all existing I-75 traffic lanes remained open during peak hours.
Night Work
In order to maintain the construction schedule and to minimize the impact to the public, it was necessary for the contractor to also work at night. Lane closures, traffic shifts, and traffic paces were used during different phases of the project.
Lane Closure Hours were:
9 p.m. to 6 a.m.
Related Projects (FDOT)
- Other FDOT I-75 Projects
- Other FDOT Hillsborough County Projects
- Other FDOT Pasco County Projects
- Other FDOT Hernando County Projects
- Other FDOT Hillsborough/Pasco County Projects
- Other FDOT Tampa Bay Area: FDOT District 7 Projects
- Other FDOT Hillsborough County/Pasco County Projects
- Other FDOT Pasco/Hernando/Sumter counties Projects
Southbound I-275 exit to westbound SR 60 may be closed at night
Posted 4/15/2016 8:00:00 AM
Left turn lanes reopened on Thonotosassa Road, south of I-4
Posted 4/15/2016
Night lane closures on I-75 in upper Pasco County
Posted 4/20/2016
What is TBI?
TBi stands for Tampa Bay Interstates - a program of the Florida Department of Transportation, District 7.