I-75 from Pasco County line to Lockhart Road (median guardrail, completed July 2009)
Project Description
Financial Project # 423464
Project Limits: Pasco County line to Lockhart Road
Project Length: 3.8 miles
Construction Cost: $972,000
Contractor: Cornerstone Businesses Inc.
Start Date: March 23, 2009
Completed: July 12, 2009
About this Project
The Florida Department of Transportation's contractor, Cornerstone Businesses Inc., installed new guardrail in the median. Various other improvements were also done in the median of Interstate 75, including building crossover areas for emergency vehicles.
Lane Closures
Lane closure hours: 7:00 p.m. to 5:30 a.m.
Related Projects (FDOT)
- Other FDOT I-75 Projects
- Other FDOT Hillsborough County Projects
- Other FDOT Pasco County Projects
- Other FDOT Hernando County Projects
- Other FDOT Hillsborough/Pasco County Projects
- Other FDOT Tampa Bay Area: FDOT District 7 Projects
- Other FDOT Hillsborough County/Pasco County Projects
- Other FDOT Pasco/Hernando/Sumter counties Projects
Southbound I-275 exit to westbound SR 60 may be closed at night
Posted 4/15/2016 8:00:00 AM
Left turn lanes reopened on Thonotosassa Road, south of I-4
Posted 4/15/2016
Night lane closures on I-75 in upper Pasco County
Posted 4/20/2016