I-75 from north of State Road 52 to northeast of County Road 577 (completed July 2007)
Project Description
Financial Project # 416727
Project Length: 5.55 miles
Construction Cost: $3.2 million
Contractor: Ajax Paving, Inc.
Start Date: January 8, 2007
Completion Date: July 11, 2007
About this Project
The Florida Department of Transportation's (FDOT) contractor has completed adding guardrail in the median of Interstate 75 from State Road 52 to a point northeast of County Road 577 in Pasco County, Florida. Most of the work was done during the daytime in the grass median.
Lane Closure Hours for mainline I-75
* 7 p.m. to 5:30 a.m.
Related Projects (FDOT)
- Other FDOT I-75 Projects
- Other FDOT Hillsborough County Projects
- Other FDOT Pasco County Projects
- Other FDOT Hernando County Projects
- Other FDOT Hillsborough/Pasco County Projects
- Other FDOT Tampa Bay Area: FDOT District 7 Projects
- Other FDOT Hillsborough County/Pasco County Projects
- Other FDOT Pasco/Hernando/Sumter counties Projects
Southbound I-275 exit to westbound SR 60 may be closed at night
Posted 4/15/2016 8:00:00 AM
Left turn lanes reopened on Thonotosassa Road, south of I-4
Posted 4/15/2016
Night lane closures on I-75 in upper Pasco County
Posted 4/20/2016