I-275 Sound Barrier Walls from Busch Blvd. to U.S. 41 Overpass (completed April 2007)
Project Description
Financial Project # 258443
Project Length: 4.7 miles
Construction Cost: $13.6 million
Contractor: Hubbard Construction Company
Start Date: February 13, 2006
Completed: April 11, 2007
About this Project
The Florida Department of Transportation's (FDOT) contractor has completed installing sound barrier walls in many areas along the I-275 corridor between Busch Boulevard and the U.S. 41 overpass (north of Bearss Avenue).
Approximately 20,000 linear feet of precast wall was installed along the FDOT right-of-way and about 400 feet of cast-in-place wall was constructed on the I-275 bridges over Linebaugh Avenue and Bougainvillea Avenue.
A traffic control plan was used to minimize inconvenience to the traveling public. However, periodic nighttime closures were necessary for mainline travel lanes.
Lane Closure Hours were
* Mainline: 9:30 p.m. to 6 a.m.
* Central Ave., Florence Ave., Linebaugh Ave., Bouganvillea Ave.: 9 a.m. to 4 p.m. and 7 p.m. to 7 a.m.
Recent Project Photos
Maps
- Wall locations: Design Section 1 (north of Busch Blvd. to south of Fowler Ave.)
- Wall locations: Design Section 2 (south of Fowler Ave. to south of Fletcher Ave.)
- Wall locations: Design Section 3 (south of Fletcher Ave. to U.S. 41 overpass)
Fact Sheets
Related Projects (FDOT)
Southbound I-275 exit to westbound SR 60 may be closed at night
Posted 4/15/2016 8:00:00 AM
Left turn lanes reopened on Thonotosassa Road, south of I-4
Posted 4/15/2016
Night lane closures on I-75 in upper Pasco County
Posted 4/20/2016