Interstate 375 from I-275 to 4th Street North (rehabilitation, completed September 2006)
Project Description
Financial Project # 408730
Project Length: 1.01 miles
Estimated Construction Cost: $2.23 million
Contractor: Kiewit Southern Co.
Start Date: May 1, 2006
Completed: September 20, 2006
About this Project
The Florida Department of Transportation's (FDOT) contractor has completed rehabilitating the concrete travel lanes and interchange ramps of Interstate 375 from I-275 to 4th Street North in St. Petersburg, Florida.
A diamond grinding process was used after the rehabilitation was completed to provide a smooth roadway surface.
Asphalt shoulder rehabilitation of the same areas was also performed during the course of the project. Other improvements consisted of milling, resurfacing, signing and pavement markings, guardrail, traffic monitoring sites, and drainage improvements.
A traffic control plan was developed and used to minimize inconvenience to the traveling public.
Related Projects (FDOT)
Southbound I-275 exit to westbound SR 60 may be closed at night
Posted 4/15/2016 8:00:00 AM
Left turn lanes reopened on Thonotosassa Road, south of I-4
Posted 4/15/2016
Night lane closures on I-75 in upper Pasco County
Posted 4/20/2016