I-75 / County Road 672 Interchange (completed March 2005)
Project Description
Financial Project # 411534
Project Length: .071 miles
Construction Cost: $4.47 million
Contractor: Zep Construction, Inc.
Start Date: October 26, 2004
Completed: March 24, 2005
About this Project
The Florida Department of Transportation (FDOT) has completed replacing the concrete bridge decks of I-75 over County Road 672 (Big Bend Road) in southern Hillsborough County, Florida. The bridge deck replacement work required the three through-lanes in either direction of I-75 to be reduced to two lanes around-the-clock (using barrier wall). Nighttime lane reductions down to one lane were permitted during the hours listed below.
In addition to the deck replacement, the northbound entrance ramp and the southbound exit ramp were resurfaced.
A minimum of one through-lane and turn lanes were maintained in each direction on CR 672. There were no lane closure hour restrictions on this road.
I-75 Lane closure hours
* 9 p.m. to 5 a.m.
Work Zone Speed Limits were:
* I-75: maintained at 60 MPH.
* CR 672: maintained at 45 MPH.
Related Projects (FDOT)
- Other FDOT I-75 Projects
- Other FDOT Hillsborough County Projects
- Other FDOT Pasco County Projects
- Other FDOT Hernando County Projects
- Other FDOT Hillsborough/Pasco County Projects
- Other FDOT Tampa Bay Area: FDOT District 7 Projects
- Other FDOT Hillsborough County/Pasco County Projects
- Other FDOT Pasco/Hernando/Sumter counties Projects
Southbound I-275 exit to westbound SR 60 may be closed at night
Posted 4/15/2016 8:00:00 AM
Left turn lanes reopened on Thonotosassa Road, south of I-4
Posted 4/15/2016
Night lane closures on I-75 in upper Pasco County
Posted 4/20/2016