Sunshine Skyway Bridge Column Repairs (completed February 2004)

Project Description

Financial Project # 4057562
Project Length: 4.1 miles
Construction Cost: $11.1 million
Contractor: M & J Construction Co.
Start Date: November 18, 2002
Completed:
February 19, 2004

About this Project
This project partially filled 71 columns on the Sunshine Skyway Bridge with concrete. Lane closures were restricted to the hours of 9 p.m. to 5:30 a.m.