Interstate 75 from SR 54 to SR 52 (median guardrail, completed May 2001)
Project Description
Financial Project # 258746
Project Length: 6.6 miles
Construction Cost: $1.9 million
Contractor: N.S. Marine & Industrial
Start Date: January 3, 2001
Completed: May 9, 2001
About this Project
Guardrail was installed down the median of Interstate 75 between State Road 54 and State Road 54 to separate the northbound and southbound traffic lanes.
Related Projects (FDOT)
- Other FDOT I-75 Projects
- Other FDOT Hillsborough County Projects
- Other FDOT Pasco County Projects
- Other FDOT Hernando County Projects
- Other FDOT Hillsborough/Pasco County Projects
- Other FDOT Tampa Bay Area: FDOT District 7 Projects
- Other FDOT Hillsborough County/Pasco County Projects
- Other FDOT Pasco/Hernando/Sumter counties Projects
Night lane closures on I-275 from Memorial Highway to downtown
Posted 3/25/2016
Left turn lanes closed temporarily on Thonotosassa Road, south of I-4
Posted 3/22/2016
Night and day lane closures on ramps at I-275/31st Street interchange
Posted 3/31/2016
What is TBI?
TBi stands for Tampa Bay Interstates - a program of the Florida Department of Transportation, District 7.