I-75 Bridge Painting

Project Description

Financial Project Number: 430802-3
Project Limits: I-75, various areas
Project Length: varies
Estimated Construction Cost: $1.3 million
Contractor: Seminole Equipment, Inc.
Contract Start Date: January 4, 2016
Estimated Completion Date: Summer 2016

About this Project
The Florida Department of Transportation's contractor is cleaning and coating all structural steel and steel bearings on various bridges over I-75, including the following bridges:

* Selmon Expressway ramp to southbound I-75.
* Northbound I-75 exit ramp to U.S. Highway 301.
* Causeway Boulevard overpass.
* Progress Boulevard overpass.

The work begins with pressure washing each bridge and then applying coats of paint.

Traffic Flow
The majority of work is being done at night when traffic volume is lighter.

Night Work
In order to maintain the construction schedule and to minimize the impact to the traveling public, lane closures are planned for nighttime hours as needed.

Lane Closure Hours
7:30 p.m. to 6:30 a.m.

Contact Person(s)

Public & Media Contact
John McShaffrey, APR
Interstate Construction Office
(813) 975-6930