Interstate 275 from the Howard Frankland Bridge to Himes Avenue (resurfacing, completed August 2002)

Project Description

Financial Project # 403738
Project Length: 4.1 miles
Estimated Construction Cost: $2.75 million
Contractor: APAC-Florida, Inc.
Start Date: February 17, 2002
Completed: August 22, 2002

About this Project
The Florida Department of Transportation (FDOT) has completed milling and resurfacing the existing asphalt pavement on the travel lanes on Interstate 275 in Hillsborough County, Florida from the Howard Frankland Bridge to Himes Avenue. The project provides a new roadway surface on the mainline interstate and ramps in this area and will allow the road surfaces to be functional until a reconstruction project begins in that area in late 2006.