Interstate 275 from south of Fletcher Avenue to north of U.S. 41 (widening, completed January 2003)

Project Description

Financial Project # 258412
Project Length: 2.3 miles
Construction Cost: $18.9 million
Contractor: Hubbard Construction Company
Start Date: May 16, 2000
Completed: January 2003

About this Project
The Florida Department of Transportation (FDOT) has completed making capacity and safety improvements to Interstate 275 in Hillsborough County, Florida from just south of Fletcher Avenue to just north of U.S. Highway 41. This project will enable more vehicles to safely use the road by adding another lane in each direction and create a safer highway corridor through interchange and lighting improvements, as well as by the concrete barrier wall that has been constructed in the median.

Improvement highlights for the I-275 corridor include:

  • Increased from a four-lane highway to a six-lane highway.
  • Improved and modified some interchange ramps.
  • Repaired concrete slabs in existing travel lanes. Ground all lanes (old and new) to provide an even surface area.
  • Constructed a median barrier wall to separate northbound and southbound interstate traffic.
  • Improved drainage and lighting.