I-4 Resurfacing from McIntosh Road to Branch Forbes Road (completed October 2012)

Project Description

Financial Project # 425084-1-52-01
Project Length: 3.2 miles
Construction Cost: $3.1 million
Contractor: Oldcastle Southern Group, Inc. D/B/A APAC-Southeast, Inc.
Start Date: March 12, 2012
Completed: October 9, 2012

About this Project
The Florida Department of Transportation's contractor removed (milled) and resurfaced (paved) the asphalt travel lanes from McIntosh Road (Exit 14) to Branch Forbes Road (Exit 17).

The resurfacing included two interchange ramps -- the eastbound exit ramp to Branch Forbes Road and the Branch Forbes entrance ramp to westbound I-4. Branch Forbes Road was also resurfaced between the interchange ramps (under I-4).

A speed limit reduction to 60 MPH was used during night work activities on the interstate.

Lane Closure Hours
* 8 p.m. to 6 a.m.

Ramp Closure Hours
* 8 p.m. to 6 a.m.