I-75 from Pasco County line to Lockhart Road (resurfacing, completed Sept. 2010)
Project Description
Financial Project Number: 422443
Project Limits: from Pasco/Hernando counties line to south of Lockhart Road
Project Length: 3.8 miles
Construction Cost: $5 million
Contractor: D.A.B. Constructors, Inc.
Start Date: March 7, 2010
Completed: September 16, 2010
About this Project
The Florida Department of Transportation's contractor has completed milling and resurfacing I-75 from the Pasco-Hernando counties line to south of Lockhart Road in Hernando County.
Improvement Highlights
- Fixed the deteriorating condition of the existing roadway for a smoother and better riding surface.
- Constructed a bridge pier protection system at the Church Road overpass.
- Replaced guardrail where needed.
The construction phasing was designed so that all existing I-75 traffic lanes remained open during peak hours.
Night Work
In order to maintain the construction schedule and to minimize the impact to the public, it was necessary for the contractor to also work at night. Lane closures, traffic shifts, and traffic paces were used during different phases of the project.
Lane Closure Hours were:
9 p.m. to 6 a.m.
Related Projects (FDOT)
- Other FDOT I-75 Projects
- Other FDOT Hillsborough County Projects
- Other FDOT Pasco County Projects
- Other FDOT Hernando County Projects
- Other FDOT Hillsborough/Pasco County Projects
- Other FDOT Tampa Bay Area: FDOT District 7 Projects
- Other FDOT Hillsborough County/Pasco County Projects
- Other FDOT Pasco/Hernando/Sumter counties Projects
Night lane closures on I-275 from Memorial Highway to downtown
Posted 3/25/2016
Left turn lanes closed temporarily on Thonotosassa Road, south of I-4
Posted 3/22/2016
Night and day lane closures on ramps at I-275/31st Street interchange
Posted 3/31/2016