I-275 Box Culvert Outfall (Howard Frankland Bridge to east of Lois Avenue, completed August 2009)

Project Description

Financial Project Numbers: 258398-4
Project Length: 2.5 miles
Estimated Construction Cost: $24 million
Contractor: Posen Construction Inc.
Start Date: January 7, 2008
Completed: August 15, 2009

About this Project
The Florida Department of Transportation's (FDOT) contractor made drainage/utility improvements from the Howard Frankland Bridge to just east of Lois Avenue.

The work under this contract consisted of constructing a drainage outfall system, box culverts, jacking and boring, storm sewers, retention ponds, and utility work.

Lane Closure Hours were
* Mainline I-275: Single lane closures from 10:00 p.m. to 5:30 a.m. Sunday through Thursday nights as needed.

* Northbound I-275 Exit 39A to State Road 60/Kennedy Boulevard: One lane may be closed on this ramp (reducing the total lanes to one) for no more than 45 consecutive days.

* West Shore Boulevard: 9:00 a.m. to 6:00 p.m.

* Lois Avenue: 9:00 a.m. to 4:00 p.m. and 7:00 p.m. to 6:00 a.m.