Tampa Bay Sunguide on I-4 from County Road 579 to Park Road (completed March 2008)

Project Description

Financial Project # 409366-2
Project Length: 11.9 miles
Construction Cost: $6.1 million
Contractor: Highway Safety Devices, Inc.
Start Date: July 13, 2006
Completed: March 21, 2008

About this Project
The Florida Department of Transportation's contractor, Highway Safety Devices, installed Intelligent Transportation System field components as part of the Tampa SunGuide Freeway Management System.

This included installation of dynamic message signs, closed circuit television, microwave detectors, and fiber optic cable along I-4 from County Road 579 to Park Road. New fiber optic cable was also installed and connected to cable installed in a previous SunGuide project.

Work to intall various components on I-4 in Ybor City was also included in this project.

Lane Closures
Lane closures were allowed as follows:

Eastbound and Westbound I-4:
10 p.m. to 6 a.m.