Tampa Bay Sunguide on I-275 from 54th Avenue North to Kennedy Boulevard (completed June 2007)
Project Description
Financial Project # 407233-2
Project Length: 10.5 miles
Estimated Construction Cost: $6 million
Contractor: Traffic Control Devices
Start Date: August 13, 2005
Completed: June 29, 2007
About this Project
The Florida Department of Transportation's contractor, Traffic Control Devices, installed Intelligent Transportation System field components as part of the Tampa SunGuide Freeway Management System. This included installation of dynamic message signs, video monitoring cameras, vehicle detection stations, fiber optic communications cable and related components along I-275 from south of 54th Avenue North to Kennedy Boulevard.
Lane Closures
Lane closures were allowed as follows:
Northbound and Southbound I-275:
10 p.m. to 5 a.m.
Ramp from westbound I-4 to southbound I-75 to be closed several nights
Posted 7/7/2017 8:00:00 AM
Night lane closures on the southbound Howard Frankland Bridge
Posted 7/7/2017
Night lane closures on southbound I-275 exit ramp to Busch Boulevard and on Busch Blvd.
Posted 7/7/2017
What is TBI?
TBi stands for Tampa Bay Interstates - a program of the Florida Department of Transportation, District 7.