City of Tampa Utility Corridor (completed January 2005)
Project Description
Financial Project # 255844-1-58-01
Project Length: .4 miles
Estimated Construction Cost: $7.8 million
Contractor: Gilbert Southern
Start Date: June 17, 2004
Completed: January 2005
About this Project
This project, which was managed by the City of Tampa, consisted of constructing a utility corridor from State Road 60 (Courtney Campbell Causeway) at the Grand Hyatt Hotel, south to Cypress Street. This work was completed in order to allow advanced relocation of multiple utilities prior to the beginning of the Tampa Airport Interchanges project and to provide an access route for the maintenance of these utilities. Organizations participating in the cost of this construction included Bright House Communications; City of Tampa Water, Wastewater, and Reclaimed Water Departments; TECO; TECO-Peoples Gas; Verizon; XO Communications; The Florida Department of Transportation; and Level 3 Communications.
Ramp from westbound I-4 to southbound I-75 to be closed several nights
Posted 7/7/2017 8:00:00 AM
Night lane closures on the southbound Howard Frankland Bridge
Posted 7/7/2017
Night lane closures on southbound I-275 exit ramp to Busch Boulevard and on Busch Blvd.
Posted 7/7/2017
What is TBI?
TBi stands for Tampa Bay Interstates - a program of the Florida Department of Transportation, District 7.