Click on an icon above to learn about projects on that road.

Night lane closures on I-275 from Memorial Highway to downtown

7/28/2014 6:15:00 AM - I-275 Widening from east of SR 60 to downtown Tampa (Hillsborough River)

TAMPA -- One to two lanes may be closed in various locations in each direction of I-275 from Memorial Highway (SR 60, Exit 39) to Ashley Drive (Exit 44) from 10:00 p.m. to 5:30 a.m. Monday through Thursday (July 28 - 31) nights.

Southbound I-275 exit to Ashley Drive to be closed at night

7/28/2014 - I-275 Widening from east of SR 60 to downtown Tampa (Hillsborough River)

TAMPA -- The portion of southbound I-275 Exit 45A to Ashley Drive will be closed from 11:30 p.m. to 5:30 a.m. Monday through Thursday (July 28 - 31) nights.

DETOUR: Use the same exit, but branch right to Doyle Carlton Drive once on the exit ramp. Turn right onto Doyle Carlton Drive, right onto Henderson Avenue, right onto Tampa Street, and then right onto Tyler Street to Ashley Drive.

Ashley/Kay/Tampa entrance ramps to southbound I-275 to be closed at night

7/28/2014 - I-275 Widening from east of SR 60 to downtown Tampa (Hillsborough River)

TAMPA -- The entrance ramps to southbound I-275 from Tampa/Kay streets and Ashley Drive will be closed from 11:30 p.m. to 5:30 a.m. Monday through Thursday (July 28 - 31) nights.

RAMP DETOURS: Traffic on Tampa/Kay streets will be directed south on Tampa Street, turn right and go west on Tyler Street, merge onto Cass Street and continue west to North Boulevard, turn right onto North Boulevard to Cypress Street, turn left onto Cypress Street and go west to Howard Avenue, turn right and go north on Howard, then turn left and use the entrance ramp at Armenia Avenue under the interstate. Ashley Drive traffic will follow the same detour, beginning by turning left onto Tyler Street.

North Boulevard closed under I-275 at night

7/28/2014 - I-275 Widening from east of SR 60 to downtown Tampa (Hillsborough River)

TAMPA -- Both directions of North Boulevard will be closed under I-275 from 10:00 p.m. to 5:30 a.m. Monday through Thursday (July 28 - 31) nights.

NORTHBOUND DETOUR: East on Laurel Street, then northwest on Green Street back to N. Boulevard.

SOUTHBOUND DETOUR: West on Main Street, south on Willow Avenue, then east on Cypress Street back to N. Boulevard.

Daytime lane closures on Mac Dill Avenue at I-275

7/28/2014 - I-275 Widening from east of SR 60 to downtown Tampa (Hillsborough River)

TAMPA -- One lane may be closed in each direction of Mac Dill Avenue under I-275 from 9:00 a.m. to 4:00 p.m. Monday through Friday (July 28 - August 1).

Mac Dill Avenue to be closed at I-275 at night

7/25/2014 - I-275 Widening from east of SR 60 to downtown Tampa (Hillsborough River)

TAMPA -- Mac Dill Avenue may be closed under I-275 from 10:00 p.m. to 5:30 a.m. Sunday through Thursday (July 27 - 31) nights.

DETOUR: Traffic will be routed around the closed area using Cypress Street, Main Street, and Howard and Armenia avenues.

Lane closure on Doyle Carlton Drive under I-275 during the day

7/25/2014 - I-275 Widening from east of SR 60 to downtown Tampa (Hillsborough River)

TAMPA -- One lane will be closed on Doyle Carlton Drive under I-275 from 9:00 a.m. to 4:00 p.m. Monday through Friday (July 28 - August 1). Watch for flaggers directing traffic.

West Shore entrance to northbound I-275 to be closed two nights

7/23/2014 - I-275 Widening from east of SR 60 to downtown Tampa (Hillsborough River)

TAMPA -- The West Shore Boulevard entrance ramp onto northbound I-275 will be closed from 11:30 p.m. to 5:30 a.m. Sunday and Monday (August 3 and 4) nights.

DETOUR: Take Kennedy Boulevard or Cypress Street east to Dale Mabry Highway, then go north on Dale Mabry to the entrance ramp at that interchange.

Southbound Himes Avenue entrance to northbound I-275 closed for several months

5/29/2014 - I-275 Widening from east of SR 60 to downtown Tampa (Hillsborough River)

TAMPA -- The southbound Himes Avenue entrance onto northbound I-275 has been closed and is expected to remain closed into September.

DETOUR: Drivers can continue south past the ramp, then turn left and go east on Cypress Street, then turn left and go north on Howard Avenue to the entrance ramp at that interchange.

Lois Avenue entrance to southbound I-275 closed for extended period

5/28/2014 - I-275 Widening from east of SR 60 to downtown Tampa (Hillsborough River)

TAMPA -- The entrance ramp onto southbound I-275 from Lois Avenue is closed for construction work in that area (closure began January 7, 2014). The ramp is estimated to remain closed until spring 2015.

DETOUR GOING TO HOWARD FRANKLAND BRIDGE: Go west on Cypress Street, turn left after crossing under State Road 60/Memorial Highway (west of O'Brien Street) and use that entrance ramp to southbound I-275 towards St. Petersburg.

DETOUR GOING TO WESTBOUND SR 60/MEMORIAL HIGHWAY: Go west on Cypress Street, turn right onto O’Brien Street and go north to Spruce Street, then turn left onto Spruce Street and go west to the ramps to westbound State Road 60/Veterans Expressway or Tampa International Airport.

Southbound I-275 Exit Ramp to Dale Mabry Highway is closed; expected to reopen in September

5/28/2014 - I-275 Widening from east of SR 60 to downtown Tampa (Hillsborough River)

TAMPA -- The southbound I-275 exit ramp (Exit 41A/B) to Dale Mabry Highway closed on May 28, 2014. It is expected to reopen in September 2014.

The signed detour route is to use Exit 41C to Himes Avenue (immediately before the Dale Mabry Highway exit), turn left at the bottom of the ramp and go south to Cypress Street, then turn right and go west on Cypress Street to Dale Mabry Highway.

Drivers are reminded that Himes Avenue is an exit from the left lane of southbound I-275.

MOTORIST ADVISORY >>> Southbound I-275 Exit 41C to Himes Avenue now a LEFT exit

12/18/2013 - I-275 Widening from east of SR 60 to downtown Tampa (Hillsborough River)

TAMPA -- The southbound I-275 Exit 41C ramp to Himes Avenue was converted into an exit from the LEFT lane of southbound I-275 on December 18.

This is a temporary change for the next phase of construction, lasting approximately into early 2015 when the exit will return permanently to a right-lane exit.

Eastbound Green Street closed next to I-275

12/10/2013 - I-275 Widening from east of SR 60 to downtown Tampa (Hillsborough River)

TAMPA -- Eastbound Green Street is closed from MacDill Avenue to Tampania Avenue (began December 9, 2013). Traffic flow will be one-way (westbound only) for approximately one year.

Laurel Street to be closed at Dale Mabry until early 2015

7/26/2013 - I-275 Widening from east of SR 60 to downtown Tampa (Hillsborough River)

TAMPA -- Laurel Street is closed from Dale Mabry Highway to 400 feet to the west until early 2015. The access from eastbound Laurel Street to the entrance ramp onto southbound I-275 is also closed. The closures began July 30. 2013.

Lois Avenue entrance to northbound I-275 closed for extended period

4/9/2013 - I-275 Widening from east of SR 60 to downtown Tampa (Hillsborough River)

TAMPA -- The entrance ramp onto northbound I-275 from Lois Avenue closed April 9, 2013. It is estimated to remain closed until late 2014.

DETOUR: Go east on Cypress Street, turn left onto northbound Dale Mabry Highway and use that road's entrance ramp to northbound I-275.